ADDRESS: 9078 Rosecrans Ave, Bellflower 90706
AREA SIZE: 11,084 SF
TIME OF COMPLETION: 187 Days
ZERO LOST-TIME INCIDENT RATE: Zero Accidents.
HIGHLIGHTS: The upgrades enhance workflow and efficiency, optimizing overall operations.
Work included preparing the building for ice cream plant equipment installation, which involved new and upgraded underground plumbing for equipment drainage, wash-down stations, and new machinery, along with the installation of a new grease interceptor. We performed electrical upgrades, installed a new rooftop unit and ductwork, and provided new concrete slabs throughout the building for walk-in freezers and coolers. Additionally, we enhanced the facility by adding new office and storage space and making interior and exterior cosmetic upgrades to improve the overall environment.